Environmental protection acceptance opinions on the completion of the power tool production line project of Zhejiang Matt Tools Co., Ltd.
2021-03-16 10:40:07

Zhejiang Matt Tools Co., Ltd. Power Tool Production Line Project


Completion of environmental protection acceptance opinions


On September 29, 2019, in accordance with the "Notice on Regulating the Environmental Protection Acceptance of Construction Units Independently Carrying Out Construction Projects", "Zhejiang Province Construction Project Environmental Protection Management Measures" (Zhejiang People's Government Order No. 364), Zhejiang Matt Tools The company established an acceptance work group to organize and convene an on-site inspection meeting for the environmental protection acceptance of the power tool production line project. The acceptance team consists of the project construction unit Zhejiang Matt Tools Co., Ltd., the acceptance monitoring report preparation unit Zhejiang Fenghe Testing Technology Co., Ltd., the environmental assessment unit Zhejiang Tianchuan Environmental Protection Technology Co., Ltd., and the exhaust gas facility design unit Yongkang Xinzhi Environmental Protection Equipment Co., Ltd. It is composed of three representatives and professional technical experts, and the list is attached.


The acceptance team conducted an on-site inspection meeting on the environmental protection facilities of the construction project in accordance with relevant national laws and regulations, technical specifications for environmental protection acceptance of construction projects, construction project environmental impact report forms and environmental impact report forms, and other requirements, and reviewed the acceptance monitoring The report and the contents of the environmental protection facility operation and management materials, in accordance with the construction project environmental protection management measures and the relevant requirements of the enterprise's independent acceptance, have formed the following acceptance opinions:


1. The basic situation of the project


(1) Construction site, scale and main construction content


Zhejiang Matt Tools Co., Ltd. is located at No. 16 Weisan East Road, Hardware Machinery Industrial Functional Zone, Tongqin Town, Wuyi County. It rents the idle workshop of Wuyi Langqi Metal Products Co., Ltd. to engage in production, forming an annual production capacity of 400,000 sets of power tools.


(2) Construction process and environmental approval status


The company passed the record of Wuyi County Development and Reform Bureau in September 2018, and the project code is 2018-330000-34-03-073676-000. In May 2019, Zhejiang Tianchuan Environmental Protection Technology Co., Ltd. was entrusted to prepare "Zhejiang Matt Tools Co., Ltd. The Environmental Impact Report Form of the Power Tool Production Line Project was approved by the Jinhua City Ecological Environment Bureau on July 11, 2019. The approval document number is Jinhuan Jianwu [2019] No. 125.


(3) Investment situation


The actual total investment of the project is 2 million yuan, of which the total investment in environmental protection is 500,000 yuan, accounting for 25% of the total investment.


(4) Scope of acceptance


The scope of this acceptance is the overall acceptance of the 400,000 sets of power tool production line project of Zhejiang Matt Tools Co., Ltd. The implementation of environmental protection equipment (measures) of the acceptance project.


2. Project changes


Production process: The production process is consistent with the environmental assessment.


Production equipment: production equipment is consistent with the environmental assessment.


In terms of raw and auxiliary materials: the type and amount of raw and auxiliary materials are consistent with the environmental assessment and match the current production capacity.


Pollution prevention and control: pollution prevention measures are consistent with the environmental assessment.


In terms of general layout: On the whole, the project production layout is consistent with the EIA description.


There are no major changes to the project.


3. Construction of environmental protection facilities


List of main pollution sources, pollutant treatment and discharge


4. Debugging effects of environmental protection facilities


"Zhejiang Matt Tools Co., Ltd. Power Tool Production Line Project Completion Environmental Protection Acceptance Monitoring Registration Form" (Fenghe Testing (2019) Yanzi No. 09-040) shows that during the acceptance monitoring period, the acceptance monitoring results are as follows:


(1) Wastewater


The daily average values of the items measured at the project’s domestic sewage outlets all meet the third-level standard in Table 4 of the Comprehensive Wastewater Discharge Standard (GB 8978-1996). Among them, the discharge of ammonia nitrogen and total phosphorus meets the local standard of Zhejiang Province "Non and phosphorus pollution in industrial enterprise wastewater Indirect Emission Limits of Chemicals" (DB 33/887-2013) other corporate standards.


(2) Exhaust gas


During the acceptance monitoring period, the emissions of styrene and non-methane total hydrocarbons in the exhaust gas of dripping paint and dipping have reached the emission limits in Table 2 of the "Industrial Coating Process Air Pollutant Emission Standard" (DB 33/2146-2018); non-methane in the welding exhaust gas Total hydrocarbon emissions meet the second-level standard in Table 2 of the "Comprehensive Emission Standard of Air Pollutants" (GB 16297-1996).


During the acceptance monitoring period, the perimeter exhaust styrene emission reached the emission limit in Table 6 of the "Industrial Coating Process Air Pollutant Emission Standard" (DB 33/2146-2018); the non-methane total hydrocarbon emission reached the "Comprehensive Air Pollutant Emission Standard" "(GB 16297-1996) Table 2 "Unorganized emission monitoring concentration limit".


(3) Noise


The noise emission at the boundary of the project reaches the standard limit of Category 3 in the Environmental Noise Emission Standard at the Boundary of Industrial Enterprises (GB 12348-2008).


(4) Solid waste


The waste enameled wire, waste metal scraps, and metal scraps generated by the project are collected and sold out; waste packaging barrels, waste emulsion, and waste activated carbon are collected and entrusted to Quzhou Qingtai Environmental Engineering Co., Ltd. for disposal; domestic waste is collected and transported by the sanitation department.


5. The impact of engineering construction on the environment


After data review and on-site inspection, the environmental assessment procedures for the approval of the power tool production line project of Zhejiang Matt Tools Co., Ltd. are complete, and the technical data is basically complete. The environmental protection facilities have been completed according to the requirements of the approved environmental impact report form and the record form. The environmental protection facilities have been inspected Qualified, its ability to prevent and control pollution meets the needs of the main project and has the conditions for the normal operation of environmental protection facilities. After deliberation, there is no unqualified acceptance as specified in the "Interim Measures for the Environmental Protection Acceptance of Construction Projects Completed" (Guohuan Gui Environmental Assessment [2017] No. 4). According to the current situation, the acceptance team agrees to the project's wastewater, waste gas, and noise environmental protection facilities Pass the environmental protection acceptance of the completed construction project.


According to the requirements of the National Environmental Regulations and Environmental Assessment [2017] No. 4 "Interim Measures for Environmental Protection Acceptance of Construction Projects", the solid waste pollution prevention and control facilities of this project should be checked and accepted by the local environmental protection authority.


6. Acceptance conclusion


Zhejiang Matt Tools Co., Ltd.’s power tool production line project has completed environmental protection procedures, implemented the "three simultaneous" requirements for environmental protection, and basically completed the acceptance documents. Environmental protection measures have been established in accordance with the requirements of the environmental assessment and approval. The environmental management system has been basically established. The main pollutant indicators meet the requirements of the corresponding pollutant discharge standards, and meet the requirements of the environmental assessment and filing form. There is no unqualified situation of acceptance as specified in the "Interim Measures for the Environmental Protection Acceptance of Construction Projects" (Guohuan Gui Environmental Assessment [2017] No. 4) , The acceptance team agreed that the environmental protection facilities for waste water, waste gas and noise of the project passed the environmental protection acceptance of the completed construction project.


According to the document requirements of the National Environmental Regulations and Environmental Assessment [2017] No. 4 "Interim Measures for the Environmental Protection Acceptance of Construction Projects", the solid waste environmental protection treatment facilities of this project should be checked and accepted by the local environmental protection authority.


7. Follow-up requirements


(1) Organize production in strict accordance with the content determined in the project environmental assessment documents and their approvals, strictly implement environmental protection laws, regulations, and standards, and strengthen information disclosure;


(2) Standardize the operation process of waste gas treatment facilities, regularly replace activated carbon, standardize the operation and management account, and ensure the stable and up-to-standard discharge of waste gas.


(3) Enterprises should improve long-term environmental protection management mechanisms, and do a good job of related environmental protection management regulations and systems.